No work on the project today.
The concrete foundation for the solar panels on the west side of the building is complete, but the foundations on the freeway (south) side of the building have not been started. After initial excavation, it was found that the soil conditions required a different design. That design has been completed, and work will resume early next week.




Leave a comment