The contractors were able to pour concrete on Wednesday. This completes work on the foundations located on the south side of the building.

With the weather delay and the design changes to the pedestal foundations behind us, it looks like the work is on schedule. The newly poured concrete will require several days to cure, a process that should be complete by early next week.
As soon as the concrete foundations are ready, three 9-foot tall pedestals will be mounted on them, using a crane to lift them in place. These pedestals will hold the "tracking" panels for the SolFocus system, which follows the movement of the sun during the day.

With the weather delay and the design changes to the pedestal foundations behind us, it looks like the work is on schedule. The newly poured concrete will require several days to cure, a process that should be complete by early next week.
As soon as the concrete foundations are ready, three 9-foot tall pedestals will be mounted on them, using a crane to lift them in place. These pedestals will hold the "tracking" panels for the SolFocus system, which follows the movement of the sun during the day.










On Monday, 2/18, the contractors were back at work. They installed the solar panels on the west side of the building, and continued foundation work on the south side.